CompTIA Project+ (PK0-004) — Question 70

Due to a lack of adherence to the risk response plan, there are numerous safety concerns within the scope of a building project.
Which of the following MOST likely explains this issue?

Answer options

Correct answer: D

Explanation

The correct answer is D because effective communication of risks is essential to ensure that all stakeholders are aware and can take appropriate action. Without communication, even identified and planned risks can lead to safety concerns. Options A, B, and C do not address the critical role of communication in managing risks.