CompTIA Project+ (PK0-004) — Question 61

A project manager must create documentation before the project kickoff meeting. Which of the following documents will identify the project, introduce the project manager, and establish authority in the project?

Answer options

Correct answer: C

Explanation

The project charter is the correct choice as it formally identifies the project, outlines its objectives, and authorizes the project manager's role. The responsibility matrix focuses on roles and responsibilities, the resource allocation plan details resource distribution, and the statement of work defines project deliverables but does not establish authority.