CompTIA Project+ (PK0-004) — Question 60
A new stakeholder has requested the status and progress reports for the project milestones. Which of the following documents should the project manager address FIRST?
Answer options
- A. Project communication plan
- B. Project status report
- C. Project management plan
- D. Project backlog
Correct answer: C
Explanation
The correct answer is C, the Project management plan, as it contains the overall framework and guidelines for the project, including communication strategies. The other options, while relevant, do not provide the comprehensive overview needed to address the stakeholder's request effectively.