CompTIA Project+ (PK0-004) — Question 568

Based on the information below:

AC=100 -

SV=80 -

EV=120 -
Which of the following is the CPI of the project?

Answer options

Correct answer: C

Explanation

The Cost Performance Index (CPI) is calculated using the formula CPI = EV / AC. In this case, CPI = 120 / 100, which equals 1.2. The other options are incorrect as they do not reflect the correct calculation of CPI.