CompTIA Project+ (PK0-004) — Question 568
Based on the information below:
AC=100 -
SV=80 -
EV=120 -
Which of the following is the CPI of the project?
Answer options
- A. 0.8
- B. 0.83
- C. 1.2
- D. 1.25
Correct answer: C
Explanation
The Cost Performance Index (CPI) is calculated using the formula CPI = EV / AC. In this case, CPI = 120 / 100, which equals 1.2. The other options are incorrect as they do not reflect the correct calculation of CPI.