CompTIA Project+ (PK0-004) — Question 569

A company recently went through a project requiring new equipment, new software, and retraining of personnel. This is MOST likely a result of:

Answer options

Correct answer: C

Explanation

The correct answer is C, as changes in business processes often necessitate new tools and training to improve efficiency and effectiveness. Options A, B, and D do not directly imply the need for such extensive changes in equipment, software, and training as a business process change does.