CompTIA Project+ (PK0-004) — Question 567
A critical stakeholder has requested additional status updated beyond the schedule.
Which of the following factors MOST likely needs to be accounted for when communication with this stakeholder?
Answer options
- A. Confidentiality
- B. Criticality
- C. Frequency
- D. Cultural differences
Correct answer: C
Explanation
The correct answer is C, Frequency, because the stakeholder's request for additional updates indicates a need for more regular communication. While confidentiality, criticality, and cultural differences are important factors, they are not directly relevant to the need for more frequent updates in this context.