CompTIA Project+ (PK0-004) — Question 555

A vendor specifies several enhancement options in a project's SOW. The project manager receives approval for a budget increase to proceed with the enhancements. Which of the following should the project manager do NEXT?

Answer options

Correct answer: B

Explanation

The correct answer is B because it is crucial to formally identify and document the change for proper tracking and accountability. While evaluating the impact (C) and communicating with the team (D) are important, they come after the change has been officially recognized and documented. Identifying the approval authority (A) is not necessary at this stage since the approval has already been granted.