CompTIA Project+ (PK0-004) — Question 556
A gate review also is considered:
Answer options
- A. a method to make changes to resources.
- B. an update to an incident response plan.
- C. a checkpoint to review schedule changes.
- D. a type of audit occurring during the project.
Correct answer: C
Explanation
The correct answer, C, identifies a gate review as a crucial point for evaluating any changes in the project schedule. Options A and B are incorrect as they relate to resource management and incident response, respectively, which do not align with the purpose of a gate review. Option D, while related to audits, does not accurately describe the primary function of a gate review in the project lifecycle.