A project stakeholder is disappointed the team was not included in some key decisions. This resulted in extra discussions and rework. Which of the following documents should the project manager review and update to resolve this situation?

Answer options

Correct answer: C

Explanation

The RACI chart defines roles and responsibilities, ensuring all stakeholders are involved in key decisions. By updating this chart, the project manager can clarify who should be consulted or informed, preventing similar issues in the future. The other options, while helpful for collaboration and information sharing, do not specifically address the need for stakeholder involvement in decision-making.