CompTIA Project+ (PK0-004) — Question 552

A change request has been submitted to change the construction material from cinder block to wood frame. Which of the following should be performed FIRST after the change has been approved by the sponsor?

Answer options

Correct answer: B

Explanation

The first step should be to conduct a quality check to ensure that the new material meets the required standards before any further actions are taken. While documentation updates, team approvals, and impact analysis are important, they come after ensuring that the quality of the new construction material is acceptable.