CompTIA Project+ (PK0-004) — Question 539

A project is approaching its end when the project manager is informed that a deliverable is exceeding the upper noise limit set by the legislation of the country where it was implemented.
Which of the following constraints has MOST likely been overlooked?

Answer options

Correct answer: C

Explanation

The correct answer is C, Environment, as it pertains to regulatory compliance and environmental factors that need to be considered during project execution. The other options, while important, do not specifically relate to the legal standards regarding noise levels, which is an environmental concern.