CompTIA Project+ (PK0-004) — Question 540
Which of the following documents would a project manager utilize to find a vendor for an undefined project?
Answer options
- A. RFP
- B. RFI
- C. RFQ
- D. SOW
Correct answer: B
Explanation
The correct answer is B, RFI (Request for Information), which is used to gather information about potential vendors when project requirements are not yet fully defined. RFP (A) and RFQ (C) are more specific and typically require defined project parameters, while SOW (D) outlines the work to be performed but does not help in vendor selection.