CompTIA Project+ (PK0-004) — Question 528
At the midway point of execution, the project plan calls for a full review of the risk register. To which of the following is the appropriate party to communicate the official results of this review?
Answer options
- A. All stakeholders
- B. Executive decision team
- C. Full project team
- D. Steering committee
Correct answer: A
Explanation
The correct answer is A, as all stakeholders need to be informed about the results of the risk register review to ensure transparency and collective understanding. The executive decision team, full project team, and steering committee may have specific roles, but they do not encompass the entire group of stakeholders who should be kept in the loop.