CompTIA Project+ (PK0-004) — Question 527
During the initiation phase of a project, a project manager is planning to schedule a meeting with stakeholders, sponsors, and other key resources. The project manager is scheduling the:
Answer options
- A. gate review meeting.
- B. stand-up meeting.
- C. kickoff meeting.
- D. planning meeting.
Correct answer: C
Explanation
The correct answer is C, as a kickoff meeting is specifically designed to bring together all major participants at the project's outset to align goals and expectations. Options A, B, and D refer to different types of meetings that serve distinct purposes and do not specifically focus on initiating the project with all key stakeholders.