The AC plus ETC is known as:
Answer options
- A. earned value.
- B. earned at completion.
- C. budget at completion.
- D. variance at completion.
Correct answer: B
Explanation
The correct answer is 'earned at completion' (B) because it specifically represents the total value of work that is expected to be completed at the end of the project. The other options refer to different project management metrics that do not combine AC and ETC in the same manner.