CompTIA Project+ (PK0-004) — Question 525
Three months into a project, the project sponsor asks the project manager for the amount of money that has been spent on the project at that point. The project sponsor is asking for the:
Answer options
- A. AC
- B. ROI
- C. BAC
- D. CPI
Correct answer: A
Explanation
The correct answer is AC, which stands for Actual Cost, indicating the total expenses incurred at that point in the project. ROI (Return on Investment) measures the profitability of the project, BAC (Budget at Completion) indicates the total budget, and CPI (Cost Performance Index) assesses cost efficiency, none of which directly answer the sponsor's request for spending.