CompTIA Project+ (PK0-004) — Question 524
Which of the following BEST describes an advantage of the Agile methodology in project management?
Answer options
- A. Ensures the project stays on schedule
- B. Readily adapts to new and changing requirements
- C. Provides the project sponsor with additional information
- D. Provides structure for newer, inexperienced project teams
Correct answer: B
Explanation
The correct answer is B, as Agile methodology is designed to be flexible and responsive to changing requirements, allowing teams to adapt quickly. Option A is incorrect because while Agile aims to keep projects on track, it does not guarantee strict adherence to schedules. Option C is not the primary focus of Agile, which emphasizes team and customer collaboration over detailed reporting. Option D is misleading, as Agile can be challenging for inexperienced teams without proper guidance.