CompTIA Project+ (PK0-004) — Question 511
A Scrum team is completing a sprint; however, some tasks will need to carry over to the next sprint.
Which of the following should the Scrum master do to improve the team's velocity in the next sprint?
Answer options
- A. Take a more hands-on leadership approach.
- B. Add the unfinished work to the backlog.
- C. Schedule a sprint retrospective.
- D. Hold additional daily stand-up meetings.
Correct answer: C
Explanation
The correct answer is C because a sprint retrospective allows the team to reflect on their performance and identify areas for improvement, which can directly enhance their velocity. Options A, B, and D do not address the need for reflection and improvement; instead, they focus on management style, task management, and meeting frequency, which may not effectively solve the underlying issues affecting the team's velocity.