CompTIA Project+ (PK0-004) — Question 510

A project has just begun, and people are not clear about the objectives.
Which of the following meeting types is needed?

Answer options

Correct answer: D

Explanation

The correct answer is D, Kickoff, as this type of meeting is specifically designed to align the team on project objectives and goals at the beginning of a project. The other options, such as A (Stand-up), B (Scheduling), and C (Impromptu), do not focus on establishing project objectives and are not suitable for this purpose.