CompTIA Project+ (PK0-004) — Question 491
A customer requests an additional requirement for the finished product. After the change is identified and documented, which of the following would be the NEXT step in the process?
Answer options
- A. Update the project documents to show the change.
- B. Evaluate the impact of the change.
- C. Implement the requested change.
- D. Submit the change request for approval.
Correct answer: B
Explanation
The next step after documenting the change is to evaluate its impact, as this assessment is crucial to understanding how the change will affect the overall project. Updating documents, implementing the change, or submitting for approval all come after this evaluation, ensuring that the project remains on track and within scope.