CompTIA Project+ (PK0-004) — Question 492
The project sponsor has asked a new project manager to create a WBS to present at the quarterly meeting with shareholders. Which of the following should be included in the WBS? (Choose two.)
Answer options
- A. Program
- B. Task
- C. Project
- D. Duration
- E. Cost variance
- F. Statement of work
Correct answer: B
Explanation
The correct answer is B, as tasks are essential components of a WBS, representing specific activities needed to complete the project. The other options, such as Program, Duration, Cost variance, and Statement of work, do not directly represent the hierarchical breakdown of work required for the project.