CompTIA Project+ (PK0-004) — Question 490
A vendor contacts the project manager regarding a particular component. The original scoped materials are no longer available, but the vendor has a replacement that can be used. Which of the following will MOST likely be impacted with the replacement material?
Answer options
- A. Resources
- B. Environment
- C. Scope
- D. Timeline
Correct answer: A
Explanation
The correct answer is A because using a different material often requires adjustments in the resources needed for the project, such as labor or equipment changes. The other options, while they may be influenced, are less directly affected by the change in materials compared to the resources required to implement the replacement.