CompTIA Project+ (PK0-004) — Question 489
A project manager sends a scheduled project newsletter to all employees of the organization. Which of the following represents the communication method the project manager used?
Answer options
- A. Pull
- B. Interactive
- C. Push
- D. Asynchronous
Correct answer: C
Explanation
The correct answer is C, Push, because the project manager is actively sending information to the employees without requiring them to seek it out. Options A and B are incorrect as Pull implies that the information must be retrieved by the recipients, and Interactive suggests a two-way communication process, which is not the case here. Option D, Asynchronous, refers to the timing of communication rather than the method used to distribute it.