The project manager for a multinational project is evaluating the option of scheduling face-to-face meetings during the release of a new system. The goal is to provide 24/7 coverage and quick responses to issues. Which of the following strategies is being applied?

Answer options

Correct answer: D

Explanation

The correct answer is D, Risk mitigation, as scheduling face-to-face meetings is a proactive approach to reduce the impact of potential issues by ensuring timely communication. Options A, B, and C do not apply here; Risk acceptance involves acknowledging risks without action, Risk avoidance means eliminating risks altogether, and Risk transference involves shifting the risk to another party.