CompTIA Project+ (PK0-004) — Question 488
The project manager for a multinational project is evaluating the option of scheduling face-to-face meetings during the release of a new system. The goal is to provide 24/7 coverage and quick responses to issues. Which of the following strategies is being applied?
Answer options
- A. Risk acceptance
- B. Risk avoidance
- C. Risk transference
- D. Risk mitigation
Correct answer: D
Explanation
The correct answer is D, Risk mitigation, as scheduling face-to-face meetings is a proactive approach to reduce the impact of potential issues by ensuring timely communication. Options A, B, and C do not apply here; Risk acceptance involves acknowledging risks without action, Risk avoidance means eliminating risks altogether, and Risk transference involves shifting the risk to another party.