CompTIA Project+ (PK0-004) — Question 486
A vendor notifies the project manager that the scheduled date for a deliverable on the critical path cannot be met due to a lack of resources. Which of the following are MOST likely to be triggered? (Choose three.)
Answer options
- A. Milestones
- B. Stakeholder changes
- C. Audits
- D. Schedule changes
- E. Incident response
- F. Business continuity response
- G. Risk register updates
Correct answer: A, D, G
Explanation
The correct actions include milestones, schedule changes, and risk register updates because these are directly related to managing project timelines and risks when a critical path deliverable is delayed. The other options, like stakeholder changes and audits, are less likely to be immediate responses to a resource issue impacting a deliverable.