CompTIA Project+ (PK0-004) — Question 485

A project manager is taking over an international project that is in progress and realizes redundant work is being performed by teams in different countries. Which of the following documents would help resolve this issue?

Answer options

Correct answer: A

Explanation

The Project scope statement clearly defines the project's boundaries, objectives, and deliverables, which can help identify and eliminate redundant tasks. The Project charter outlines the project's purpose and stakeholders but does not detail specific tasks. A Status report provides updates on the project's progress but lacks comprehensive information on scope. The Project communication plan focuses on communication strategies rather than task management.