CompTIA Project+ (PK0-004) — Question 484
Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:
Answer options
- A. Managing change
- B. Fast tracking
- C. Rolling wave planning
- D. Crashing
Correct answer: B
Explanation
The correct answer is B, as fast tracking involves overlapping tasks in a project schedule to save time. The other options do not accurately describe the scenario; managing change refers to handling project modifications, rolling wave planning is a scheduling technique for planning in iterations, and crashing involves adding resources to expedite a task.