CompTIA Project+ (PK0-004) — Question 483

The project manager is running a project in an organization with a strong PMO and a mature control process. Due to vendor delays, the project is scheduled to exceed the authorized timeline. The project manager has discovered that fast-tracking two tasks will mitigate the issue. Which of the following should the project manager do NEXT?

Answer options

Correct answer: D

Explanation

The correct answer is D because obtaining approval is essential before implementing any changes to the project schedule, especially in a controlled environment. Announcing the fast track (A) or modifying the schedule (B) without approval could lead to issues with adherence to PMO protocols. Initiating a change request (C) is a step in the process, but the immediate next action should be to secure approval for the changes.