CompTIA Project+ (PK0-004) — Question 453

According to the communication management plan, the project scheduler is required to post weekly status reports on the project's intranet site. From the stakeholders' point of view, accessing the weekly report is an example of:

Answer options

Correct answer: D

Explanation

The correct answer is D, the pull method, because stakeholders can access the report at their convenience by retrieving it from the intranet. The other options do not accurately describe this scenario; interorganizational and personal preferences refer to individual or organizational inclinations rather than the method of accessing information, while the interactive method implies direct communication rather than accessing a report.