A project manager is assigned a project that is part of the company's strategic objectives. Of which of the following is the project a part?
Answer options
- A. Project management office
- B. Portfolio
- C. Program
- D. Mission statement
Correct answer: B
Explanation
The correct answer is B, as a portfolio encompasses a collection of projects and programs that are aligned with strategic objectives. Options A and C refer to specific organizational structures for managing projects, while D is a statement of purpose and does not categorize projects.