CompTIA Project+ (PK0-004) — Question 452

While preparing to plan a project, the project manager meets with the key stakeholders to determine the flexibility between the project constraints. Which of the following techniques should the project manager consider to reduce personal bias and increase buy-in?

Answer options

Correct answer: A

Explanation

The correct answer is A, as sending an anonymous survey allows stakeholders to provide unbiased feedback about project constraints. This method is more effective than simply observing or voting, which can be influenced by dominant voices or personal biases. Options B, C, and D do not guarantee the same level of impartiality or stakeholder engagement.