CompTIA Project+ (PK0-004) — Question 451
Which of the following are the BEST risk analysis tools to determine a project's risk level? (Choose two.)
Answer options
- A. Fishbone diagram
- B. RACI matrix
- C. Monte Carlo
- D. Process flowchart
- E. Expert judgment
- F. Project dashboard
Correct answer: C, E
Explanation
The Monte Carlo method (C) is a statistical technique that allows project managers to understand potential risks by simulating various scenarios. Expert judgment (E) leverages the knowledge of experienced individuals to assess risks effectively. The other options, while useful in project management, do not specifically focus on risk analysis.