CompTIA Project+ (PK0-004) — Question 441

The business stakeholder has been engaged late and has just had a chance to review the approved requirements. Consequently, it has been identified that there are a number of gaps in the requirements which are critical to the stakeholders's business unit.
Which of the following actions should the project manager take?

Answer options

Correct answer: A

Explanation

The correct action is to initiate change control because the identified gaps in the requirements necessitate formal adjustments to the project scope. Following the communications plan, managing project quality, or preparing a performance report do not directly address the urgency of the requirement gaps.