CompTIA Project+ (PK0-004) — Question 440
Which of the following is the project phase when quality assurance occurs?
Answer options
- A. Planning
- B. Closing
- C. Execution
- D. Scoping
- E. Initiation
Correct answer: C
Explanation
Quality assurance is primarily conducted during the Execution phase of a project, as this is when the actual work is being carried out and processes can be monitored for quality. The Planning phase focuses on defining how quality will be managed, while Closing wraps up the project and does not involve active quality assurance. Scoping and Initiation phases are more about defining the project and its objectives rather than ensuring quality.