CompTIA Project+ (PK0-004) — Question 442

The project's network map has a loop with multiple project outcomes.
This is the result of which of the following scheduling tools?

Answer options

Correct answer: D

Explanation

The correct answer is D, as the Graphical evaluation and review technique can visually represent complex interdependencies, potentially leading to loops in the network map. The other options, such as establishing baselines, Critical Path Analysis, and Critical Chain Method, focus on time management and resource allocation without creating such loops.