CompTIA Project+ (PK0-004) — Question 43

A WBS is being developed for a project.
Which of the following would be BEST suited to contribute cost and time estimates for the project activities?

Answer options

Correct answer: A

Explanation

Project team members are typically the most knowledgeable about the specific tasks and activities required for the project, making them well-suited to provide accurate cost and time estimates. While the project manager and sponsor may have insights, they are often not involved in the day-to-day details that affect these estimates. The project scheduler focuses on timelines and may not have the detailed cost information necessary.