CompTIA Project+ (PK0-004) — Question 43
A WBS is being developed for a project.
Which of the following would be BEST suited to contribute cost and time estimates for the project activities?
Answer options
- A. Project team members
- B. Project sponsor
- C. Project manager
- D. Project scheduler
Correct answer: A
Explanation
Project team members are typically the most knowledgeable about the specific tasks and activities required for the project, making them well-suited to provide accurate cost and time estimates. While the project manager and sponsor may have insights, they are often not involved in the day-to-day details that affect these estimates. The project scheduler focuses on timelines and may not have the detailed cost information necessary.