CompTIA Project+ (PK0-004) — Question 44

A project manager received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes.
Which of the following should the project manager do NEXT?

Answer options

Correct answer: B

Explanation

The correct next step is to identify the approval authority, as this ensures that the project manager knows who has the power to approve the changes before proceeding. Gaining approval (option A) cannot happen until the authority is identified, implementing changes (option C) should only occur after approval, and creating an emergency change request (option D) is unnecessary in this context.