CompTIA Project+ (PK0-004) — Question 42

A vendor was removed from a company due to non-performance but continues to submit invoices for work that was not completed. Which of the following should the project manager do to stop the vendor from sending invoices?

Answer options

Correct answer: A

Explanation

The correct action is to draft a C&D letter, which formally instructs the vendor to cease their actions. Reviewing the MOU may provide insights but will not directly stop the invoices. Asking for a non-complete agreement is unnecessary since the vendor has already been removed, and meeting with finance may help but won't stop the vendor from invoicing without the formal notice.