CompTIA Project+ (PK0-004) — Question 41
Before a team can start on a sprint, they will need to:
Answer options
- A. create a set of iterations to work on and prioritize.
- B. generate an icebox of work items to review.
- C. review the backlog of work items to prioritize.
- D. take client requirements and draft them into a task list.
Correct answer: A
Explanation
The correct answer is A because creating a set of iterations to work on and prioritizing them is essential for guiding the team's efforts during the sprint. Options B, C, and D, while potentially relevant, do not specifically address the primary requirement of establishing a prioritized set of iterations before starting work.