CompTIA Project+ (PK0-004) — Question 412
A project manager is working on the project charter.
Which of the following phases does this describe?
Answer options
- A. Initiation
- B. Planning
- C. Execution
- D. Closing
Correct answer: A
Explanation
The correct answer is A, Initiation, as this phase is specifically focused on defining the project, including creating the project charter. The Planning phase involves outlining the project details, Execution is about implementing the plan, and Closing pertains to finalizing the project, none of which include the development of the project charter.