CompTIA Project+ (PK0-004) — Question 411
The client accepts the critical design review.
Which of the following meetings should be held to move to the NEXT step in the project?
Answer options
- A. Execution
- B. Kickoff
- C. Closure
- D. Planning
Correct answer: B
Explanation
The correct answer is B, as the kickoff meeting is essential to initiate the project after the design has been approved. Options A, C, and D are not appropriate as Execution refers to the implementation phase, Closure signifies project completion, and Planning is for outlining the project before proceeding.