A project manager identified a risk in a geographically unstable area. During the project, a volcano erupts, preventing project team access. Which of the following documents should the project manager update FIRST?
Answer options
- A. Project schedule
- B. Issue log
- C. Risk register
- D. Scope statement
Correct answer: B
Explanation
The correct answer is B, the Issue log, because the volcanic eruption represents an immediate issue that impacts the project. While the Risk register may need an update later, the Issue log is for current problems that require immediate attention, whereas the Project schedule and Scope statement pertain to planning and defining work rather than addressing active issues.