CompTIA Project+ (PK0-004) — Question 406
Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?
Answer options
- A. EAC
- B. BAC
- C. CPI
- D. ETC
Correct answer: C
Explanation
The Cost Performance Index (CPI) is a key indicator that helps project managers assess the cost efficiency of a project. A CPI value less than 1 signifies overspending, while a value greater than 1 indicates underspending. The other options, EAC, BAC, and ETC, are related metrics but do not directly measure whether a project is overspending or underspending.