CompTIA Project+ (PK0-004) — Question 394
The PMO is responsible for: (Choose two.)
Answer options
- A. managing the project plan, scope, risk, and budget.
- B. contributing expertise, deliverables, and estimates of costs.
- C. setting standards and practices for the organization and providing governance.
- D. outlining consequences of non-performance and coordinating between disparate projects.
- E. approving funding, developing the project schedule, and gathering high-level requirements.
Correct answer: C, D
Explanation
The PMO is primarily tasked with setting standards and governance (C) to ensure project alignment with organizational goals. Additionally, they coordinate between different projects and define consequences for non-performance (D), which helps in maintaining overall project integrity. The other options, while relevant to project management, do not specifically describe the PMO's core responsibilities.