CompTIA Project+ (PK0-004) — Question 394

The PMO is responsible for: (Choose two.)

Answer options

Correct answer: C, D

Explanation

The PMO is primarily tasked with setting standards and governance (C) to ensure project alignment with organizational goals. Additionally, they coordinate between different projects and define consequences for non-performance (D), which helps in maintaining overall project integrity. The other options, while relevant to project management, do not specifically describe the PMO's core responsibilities.