CompTIA Project+ (PK0-004) — Question 393

A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints.
Which of the following documents should the project manager use to obtain this information?

Answer options

Correct answer: D

Explanation

The correct answer is D, the Status report, as it typically provides an overview of project progress, including completion percentages, schedule updates, and budget status. The Project schedule (A) mainly outlines the timeline, while the Balanced scorecard (B) focuses on performance measures and goals, and the Issue log (C) tracks problems rather than overall project status.