The project sponsor has cut the resources required for project completion. The project manager cannot complete the project without additional resources.
Which of the following should the project manager do to obtain the resources?

Answer options

Correct answer: A

Explanation

The correct answer is A because submitting a change request with documented reasons is a formal process to request additional resources. Options B and C are not advisable as they do not follow the proper project management protocols, while option D could lead to burnout among team members and may not solve the resource issue.