CompTIA Project+ (PK0-004) — Question 391

A project team is performing change control on a project. During which of the following project activities does this normally occur?

Answer options

Correct answer: C

Explanation

Change control is primarily a part of the Planning phase, where adjustments to the scope, schedule, or resources are identified and assessed. While monitoring, execution, and closing are critical project activities, they do not focus specifically on formalizing changes in the project plan like the planning phase does.