CompTIA Project+ (PK0-004) — Question 389
Assuming an iterative approach, which of the following will be conducted at the end of each iteration?
Answer options
- A. SCRUM retrospective
- B. Kickoff meeting
- C. Budget baseline
- D. Risk review
Correct answer: A
Explanation
The SCRUM retrospective is a key practice in agile methodologies where the team reflects on the past iteration to identify improvements. The other options, such as the Kickoff meeting, are typically conducted at the start of a project, while the Budget baseline and Risk review are not necessarily tied to the end of each iteration.