CompTIA Project+ (PK0-004) — Question 383

A project task has been completed ahead of schedule. Which of the following is the MOST appropriate next step?

Answer options

Correct answer: B

Explanation

The correct answer is B because communicating success to the team fosters motivation and acknowledges their effort. The other options, while relevant, do not prioritize team morale or recognition; A focuses on task assignment, C on informing stakeholders, and D on schedule adjustments, which may not be immediate concerns.