A project task has been completed ahead of schedule. Which of the following is the MOST appropriate next step?
Answer options
- A. Provide the next task to the newly freed resource.
- B. Communicate the success to the team.
- C. Notify the project sponsor of the new completion date.
- D. Update the schedule and add lag to the next task.
Correct answer: B
Explanation
The correct answer is B because communicating success to the team fosters motivation and acknowledges their effort. The other options, while relevant, do not prioritize team morale or recognition; A focuses on task assignment, C on informing stakeholders, and D on schedule adjustments, which may not be immediate concerns.