CompTIA Project+ (PK0-004) — Question 384
A fire alarm goes off in the building where the project team works. Employees are instructed to leave the premises immediately using the stairs; they are not to use elevators, and they must gather in one place outside the building for further instructions. This is known as a:
Answer options
- A. business change response
- B. change management response
- C. business continuity response
- D. risk management response
Correct answer: D
Explanation
The correct answer is D, as risk management response involves procedures that are activated in emergencies to ensure safety and minimize potential dangers. Options A, B, and C do not specifically address the immediate actions taken in response to a fire alarm, which is primarily focused on risk management.